As many non-essential employees across the state are telecommuting as we all work together to flatten the curve and combat COVID-19, the MTA’s and LIRR’s essential workers and contractors continue safely transporting health care workers, first responders and other essential workers to and from their jobs. These transportation not only…
The Plainfield Avenue Bridge, located in the Village of Floral Park along the Main Line, received a new single-track bridge to accommodate the additional track with the LIRR Expansion Project. The Plainfield Avenue Bridge has been in service since 1958.
Support of excavation work has begun for the new Plainfield Avenue bridge in Floral Park, one of several bridges that have been or will be replaced as part of the LIRR Expansion project from Floral Park to Hicksville. Once this phase of construction is complete, work will start on the…
The LIRR Expansion Project team continues to work closely with officials from Floral Park as construction activities continue in the Village. The project team recently held a productive coordination meeting with the Mayor and Village officials to discuss several ongoing items, including: installation of retaining walls air quality monitoring coordination…
As part of the LIRR Expansion Project, Design-Build Contractor 3TC continues to meet environmental commitments in Project-adjacent communities. 3TC recently installed an air quality monitoring station in Floral Park near area residents to ensure ongoing construction activities on the LIRR right-of-way and in the Village do not exceed allowable thresholds….
Happy Birthday, Long Island Rail Road! The LIRR turned 185 years old on April 24, and former LIRR branch manager and current LIRR historian Dave Morrison and others sat down with Newsday to reminisce about the railroad’s eventful history. Stephen Quigley, president of the Long Island Sunrise Trail Chapter of…
On April 24th, the LIRR Expansion Project team hosted the monthly Mayors’ meeting at the LIRR Expansion Project Community Information Center in Mineola. Village and Town officials throughout the Project corridor convened to discuss ongoing construction activities: Tom McGuinness, MTACC Deputy Project Director, discussed recent construction milestones and provided an…
The LIRR Expansion Project has extended the deadline for Q1 Community Scorecard submissions until the end of the day on Friday, May 3rd. As part of LIRR Expansion Project, the MTA has developed a series of environmental and community commitments in coordination with communities adjacent to the project to minimize…
As part of the LIRR Expansion Project Floral Park to Hicksville, the MTA has developed a series of environmental and community commitments in coordination with the project-adjacent communities to minimize construction-related impacts: the MTA has established the Design-Builder Incentive Program, a monetary fund to incentivize Design-Build Contractor 3rd Track Constructors…
On April 10th, members of the Suffolk County Economic Development team joined the LIRR Expansion Project team at the Community Information Center in Mineola to discuss ongoing progress. The team presented a project overview and showcased the latest construction milestones at the South Tyson Avenue Bridge modification, the Covert Avenue…
As construction continues at the South Tyson Avenue Bridge in the Village of Floral Park, crossing guards and flaggers are ensuring the safety of pedestrians by helping them navigate around the construction area. The implementation of these measures at South Tyson Avenue is consistent with the LIRR Expansion Project team’s…